12 men complete a work in 9 days. After they have worked for 6 days, 6 more men join them. How many days will they take to complete the remaining work?
-
2
-
3
-
4
-
5
A.
2
P.D. = P.D. (Persons x no of days)
12 x 9 = 12 x 6 + (12+6) x d
108 = 72 + 18d
18d = 36
d = 2 days