Question
CLATENEM12019267

‘A’ and ‘B’ complete a work in 12 days, ‘B’ and ‘C’ in 8 days and ‘C’ and ‘A’ in 16 days. ‘A’ left after working for 3 days. In how many days more will ‘B’ and ‘C’ finish the remaining work?

  • 6

  • 3 ¾

  • 7 ¾

  • 4 ¾

Solution

D.

4 ¾

Sponsor Area

Question
CLATENEM12019277

‘A’ and ‘B’ complete a work in 12 days, ‘B’ and ‘C’ in 8 days and ‘C’ and ‘A’ in 16 days. ‘A’ left after working for 3 days. In how many days more will ‘B’ and ‘C’ finish the remaining work?

  • 6

  • 3 ¾

  • 7 ¾

  • 4 ¾

Solution

D.

4 ¾

Question
CLATENEM12019237

10 sheep and 5 pigs were brought for Rs. 6,000. If the average price of a sheep is Rs.
450, find the average price of pig.

  • Rs. 380

  • Rs. 410

  • Rs. 340

  • Rs. 300

Solution

D.

Rs. 300

Question
CLATENEM12019213

100, 50, 33.33, ...., 20

  • 25

  • 30

  • 21

  • 22

Solution

A.

25

Question
CLATENEM12019217

117, 104, 91, 78 ?

  • 39

  • 60

  • 65

  • 68

Solution

C.

65

13